Construction Update · 6 August 2026
Foundation Works Continue: Progress Across Site

Work continues across the site after the initial concrete pour completed in late July. The team is now working through the remaining foundation sections in stages.
Aerial photos from August 6th show the current state of the site. Several foundation bays are at different stages — some have been poured and are curing, while others have formwork and steel in place ready for concrete.
The staged approach means crews can keep moving while earlier sections cure. It also makes it easier to manage materials and truck deliveries without holding up progress.
Steel reinforcement has been placed and tied in multiple areas. Inspections are completed before each pour to verify everything meets spec.
Ground conditions have stayed stable. No major issues with water or soil movement. Compaction testing on the sub-base passed requirements.
The schedule remains on track. Once all foundation sections are complete and cured, formwork comes off and the site will be ready for framing to begin.